Key Points

The Telangana government has initiated a critical process to rehabilitate the Kaleshwaram Lift Irrigation Project's barrages following an extensive National Dam Safety Authority investigation. The project, which was constructed during the previous BRS government, has been found to have significant structural deficiencies and design flaws. An Expression of Interest has been invited to engage reputed design agencies for comprehensive restoration of Medigadda, Annaram, and Sundilla barrages. The move comes after the state government aims to address the serious technical issues that could compromise the project's integrity and future functionality.

Key Points: Telangana Seeks Design Help for Kaleshwaram Barrage Repairs

  • Telangana issues EOI for rehabilitation of Medigadda, Annaram, and Sundilla barrages
  • NDSA committee recommends comprehensive design review for project
  • Structural issues discovered in Kaleshwaram Lift Irrigation Project
  • Irrigation Minister highlights previous government's project failures
3 min read

Telangana govt initiates move for restoration of Kaleshwaram barrages

Telangana govt invites experts to rehabilitate Kaleshwaram project barrages after NDSA investigation reveals critical structural issues

"Based on inferences drawn from various investigations and studies, a suitable rehabilitation plan must be designed and implemented. - NDSA Committee Report"

Hyderabad, Oct 1

The government of Telangana has invited Expression Of Interest (EOI) for rehabilitation and restoration of designs and drawings of the Medigadda, Annaram and Sundilla barrages of the Kaleshwaram Lift Irrigation Project.

The Irrigation and Command Area Development Department invited EOI for empanelment of reputed design agencies for rehabilitation and restoration designs of the three barrages based on the investigations carried out as per the directions of the National Dam Safety Authority (NDSA) committee.

Proposal for EOI have to be submitted before October 15, Chief Engineer, Central Designs Organisation, said in a notification.

The NDSA committee, which conducted a thorough probe into the project after some piers of Medigadda barrage sank in October 2023, in its final report in April 2025 recommended the preparation of a rehabilitation design for all the three barrages.

"Based on inferences drawn from various investigations and studies, a suitable rehabilitation plan must be designed and implemented. The Committee recommends that the Irrigation Department engage reputed institutions and departments for these tasks. Given the design complexities, the rehabilitation design should preferably be reviewed by the Central Water Commission," the report stated.

The final report, spanning 378 pages and 16 chapters, notes in its 'Recommendations on the way forward' that issues such as sand piping, cavity formation beneath the raft, construction flaws, and design deficiencies -- already observed in Block 7 of the Medigadda barrage -- could also affect other blocks.

The report stated that issues such as sand piping, cavity formation beneath the raft, construction flaws, and design deficiencies observed in Block 7 of the Medigadda barrage could also affect other blocks.

The NDSA concluded that upstream barrages, Annaram and Sundilla, which exhibit similar design and construction flaws, have experienced structural distress and damage, rendering them unserviceable.

Last month, Irrigation Minister N. Uttam Kumar Reddy had directed the department officials to get going on identifying and selecting design consultants for the required repairs to the barrages.

The minister had also stated that NDSA report was a direct indictment of the previous BRS government, exposing serious flaws in its design, construction and maintenance.

The Minister accused the previous BRS government of mortgaging Telangana's future by borrowing over Rs. 1 lakh crore at high interest rates to build a project that collapsed during its regime.

The P.C. Ghose Commission, which probed the alleged irregularities in the Kaleshwaram project, submitted its report to the state government on July 31, 2025.

The Commission headed by the former judge of the Supreme Court was constituted on March 14, 2024 to probe the irregularities in planning, design, construction, quality control, operation and maintenance of Medigadda, Annaram and Sundilla Barrages of the Kaleshwaram project constructed during the term of previous BRS government.

Following a marathon debate on the report in the Assembly on August 31, Chief Minister Revanth Reddy announced that the case relating to irregularities in the project will be handed to the Central Bureau of Investigation.

- IANS

Share this article:

Reader Comments

P
Priya S
As someone from a farming family in Telangana, this project's failure has directly affected our livelihoods. The government must ensure that the new designs are thoroughly vetted by experts. We can't afford another failure - farmers are already struggling with water scarcity.
M
Michael C
The technical details in the NDSA report are quite concerning - sand piping, cavity formation, construction flaws. This shows the importance of proper engineering standards in infrastructure projects. Hope they engage the best design agencies this time.
A
Aditi M
While I appreciate the current government taking action, I hope this doesn't become another political blame game. The focus should be on fixing the technical issues and ensuring water security for Telangana. The CBI investigation should be fair and transparent.
S
Suresh O
Rs. 1 lakh crore project collapsing due to design flaws is unacceptable! The taxpayers' money deserves better accountability. The officials and contractors responsible must be held accountable. This sets a bad precedent for infrastructure development in India. 😠
K
Kavya N
Good to see the government moving quickly with EOI process. The involvement of National Dam Safety Authority and Central Water Commission gives me confidence that this restoration will be done properly. Hope they complete it before the next agricultural season.

We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.

Leave a Comment

Minimum 50 characters 0/50