Key Points

NALCO is making a massive Rs 30,000 crore investment to significantly expand its operations over the next five years. The expansion includes increasing bauxite mining capacity, adding alumina refining capabilities, and building new smelter and power plants. This ambitious plan comes on the heels of record financial performance with a 77% profit jump in Q1 FY26. The company aims to achieve Maharatna status by 2030 while strengthening its complete aluminum production value chain.

Key Points: NALCO Invests Rs 30000 Crore for Smelter and Power Plant Expansion

  • Rs 30,000 crore investment to expand bauxite mining capacity to 11 million tonnes
  • Adding 1 million tonnes alumina refining capacity starting June next year
  • New 5 lakh tonne smelter plant and 1000 MW captive power plant planned
  • Aims to achieve Maharatna status by 2030 with strengthened value chain
3 min read

NALCO to invest Rs 30,000 crore for expansion by 2030

State-owned NALCO announces Rs 30,000 crore expansion to boost bauxite mining, alumina refining, and smelting capacity by 2030, aiming for Maharatna status.

"We are adding one more smelter of 5 lakh tonnes... that will make our capacity around maybe 9.6 lakh tons - CMD Brijendra Pratap Singh"

New Delhi, August 28

State-owned aluminium producer National Aluminium Company Limited (NALCO) is set to invest Rs 30,000 crore as part of its expansion plans over the next 5 years through 2030.

The expansion plans include setting up of a smelter plant and a captive coal power plant, CMD Brijendra Pratap Singh told reporters Thursday.

"Our existing mining capacity, bauxite mining capacity, is 75 lakh tonnes. We are adding one mine...which will be a 3 million tonnes mine. So from 7.5 million tonnes, we'll be going to maybe 10.5 or maybe 11 million tonnes of bauxite mining.. This will start in next one year."

As far as alumina is concerned, refining alumina chemical production, NALCO's existing capacity is 2.1 million tonnes.

"We are adding 1 million tonnes more alumina capacity. This will start in next year June. So next year June, we will start the commissioning process. It will take some time in the commissioning, maybe next financial year ending our alumina capacity will become 3.1 million tonnes."

It has smelting capacity is 4.6 lakh tonnes.

"Our plan is that we have to add one more smelter and that will take around four years. One more smelter of 5 lakh tonnes. So that will make our capacity around maybe 9.6 lakh tons," the CMD said.

Along with that, it currently has a 1200 megawatt power plant.

"We will be adding 1000 megawatt of power plant (as part of the expansion)," the CMD said.

Bhubaneswar-headquartered NALCO, a Navratna company, aims to become a Maharatna company by 2030, the CMD said.

Separately, the company has reported strongest financial performance in the first quarter of FY 2025-26. NALCO recorded a net profit of Rs 1064 crore, marking a 77% increase from Rs 601 crore during the same period last year.

This builds on a landmark FY 2024-25, during which the company posted its highest-ever annual net profit of Rs 5325 crore, a 158% year-on-year rise, and achieved record revenue from operations of Rs 16,788 crore.

The Board today recommended a final dividend of Rs 2.50 per share, bringing the total dividend payout for the year to Rs 1928.46 crore.

In Q1 FY 2025-26, the company reported its highest-ever domestic sales of Alumina and Aluminium. Alumina exports rose by 209 percent and domestic Alumina sales increased by 190 percent, leading to a substantial jump in overall sales volumes.

Capitalising on its strong financial foundation, NALCO is advancing a series of expansion initiatives aimed at securing long-term growth and strengthening its value chain. These include Expansion of the 5th Stream of the Alumina Refinery at Damanjodi; Operationalisation of the Pottangi Bauxite Mines to ensure sustained raw material availability; Expansion of the Smelter Plant and Captive Power Plant, among others.

Currently, the Indian government owns 51.28 percent of NALCO's equity capital. The Company has been operating its captive Panchpatmali Bauxite Mines for the pit head Alumina refinery at Damanjodi, in the District of Koraput in Odisha and Aluminium Smelter, Captive Power Plant & Captive coal mines at Angul.

The Company has a 68.25 lakh TPA Bauxite Mine & 21.00 lakh TPA (normative capacity) Alumina Refinery located at Damanjodi in Koraput district of Odisha, and 4.60 lakh TPA Aluminium Smelter, 1200MW Captive Power Plant & 40.00 lakh TPA Coal Mines located at Angul, Odisha.

- ANI

Share this article:

Reader Comments

P
Priya S
Impressive growth numbers! 77% profit increase and 158% YoY rise shows how well our PSUs can perform under good leadership. Hope this expansion includes sustainable mining practices and environmental protection measures.
M
Michael C
As an investor, I'm impressed with the dividend payout of Rs 1928 crore. NALCO shares have been performing well and this expansion plan shows strong future growth potential. Good time to consider adding to portfolio.
A
Ananya R
While the expansion is welcome, I hope NALCO invests in proper rehabilitation of displaced communities and maintains ecological balance. Mining projects often affect tribal populations - hope they handle this responsibly.
V
Vikram M
This is exactly what Make in India needs! Domestic production capacity expansion reduces our import dependence. Aluminum is crucial for defense, aerospace, and infrastructure sectors. Jai Hind! 🚀
S
Sarah B
The captive power plant expansion to 1000MW is smart - ensures energy security for operations. Hope they also invest in renewable energy sources to reduce carbon footprint. Overall, well-planned growth strategy!

We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.

Leave a Comment

Minimum 50 characters 0/50