Key Points

India's renewable energy sector is showing impressive momentum with a major capacity addition. A huge pipeline of projects is currently under construction, signaling strong future growth. The cost of combining solar power with storage has hit new, attractive lows. Experts predict a surge in national power demand starting next month, further driving the sector.

Key Points: India Adds 27 GW Renewable Energy Capacity in Five Months

  • India added a robust 27 GW of gross renewable capacity in just five months
  • Another 142 GW of renewable energy projects are currently under construction
  • Solar plus energy storage system costs have fallen to a record low of Rs 2.7/kWh
  • The report anticipates a significant pickup in national power demand from late October
3 min read

India adds 27 GW renewable energy capacity in April-Aug: Report

India commissions 27 GW of renewable power from April-August, with 142 GW more under construction. Solar-storage costs hit record lows, boosting sector growth.

"“Innovative tenders continue to bring down power storage costs, which we expect will increase acceptability of renewable power.” - HSBC Report"

New Delhi, Sep 25

Renewable energy (RE) capacity commissioning momentum in India remains strong with a robust 27 GW of gross capacity added during the first five months (April-August) of the current financial year, according to a report released on Thursday.

Within this, 20GW of renewable capacity was commissioned through August. Another 142GW is under various stages of construction, as per Central Electricity Authority (CEA), according to an HSBC report.

With gradual progress on commissioning of interstate transmission lines, the commissioning of renewable projects is expected to pick up pace as well. Recent mergers and acquisitions and renewable developers' potential listings also should make more capital available to accelerate commissioning, the report states.

“Innovative tenders continue to bring down power storage costs, which we expect will increase acceptability of renewable power,” the report observed.

It highlights that the solar plus energy storage system (ESS) costs have now fallen to record lows. In a recently discovered solar plus storage tender, the tariffs discovered were as low as IRs 2.7-2.76/kWh. Based on the terms, the developer is expected to provide power for two hours during peak times and storage for another two hours during morning peak, apart from supplying the usual solar power during solar hours.

While the tariffs have raised concern on the profitability, the savings on infrastructure, low risk on land acquisition, and earnings for free power during morning peak will likely allow developers to earn normative returns, the report states.

It also expects slower tendering and focus on cleaning the old renewable auctions to ultimately restore investor confidence in the renewable energy sector. India conducted more than 90GW of renewable energy auctions in the past two years and a significant part remains unsigned into power purchase agreements (PPA). This creates uncertainty for developers and investors on the value that needs to be assigned to these award letters (LOAs), the report points out.

India has already cancelled 11.4GW of renewable tenders that met with insufficient participation or high tariffs. This could pave the way for allow some old suck tenders to be cancelled as well, it added.

The report expects the overall demand for power in the country to accelerate next month. It states that overall power demand is still tepid, although there has been a 3 per cent year-on-year increase in September.

“It’s important to highlight that power demand this month already exceeds September 2023's (a month when power demand grew 11.5 per cent year-on-year). Based on weather forecasts, likelihood of an intense winter, and expected pickup in industrial activity, is expected to lead to a meaningful pickup in power demand in late October or early November,” according to the report.

- IANS

Share this article:

Reader Comments

R
Rohit P
Good progress but we need to address the 142GW stuck in construction. The transmission infrastructure delays have been a persistent issue. Hope the interstate transmission lines get completed soon.
A
Arjun K
The storage technology breakthrough is the real game-changer here. Being able to provide power during peak hours makes renewables much more reliable. This could finally solve our evening power crunch problems! 🔋
S
Sarah B
While the numbers look impressive, I'm concerned about the 90GW of unsigned PPAs. This uncertainty isn't good for investor confidence. The government needs to streamline the auction process and ensure signed agreements.
V
Vikram M
The cancellation of 11.4GW tenders shows responsible governance. Better to cancel than proceed with unviable projects. This will help maintain quality standards in our renewable energy expansion.
K
Kavya N
Hope this renewable push creates more green jobs for our youth. The manufacturing and maintenance sectors should get a big boost. Solar panels made in India for India! 🌞

We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.

Leave a Comment

Minimum 50 characters 0/50