Himachal: Larji Power Project restored and fully operational once again

ANI May 19, 2025 244 views

The Larji Hydroelectric Project is back online after suffering severe damage during the 2023 Beas River floods. Himachal's government allocated Rs 245 crore for restoration, completing repairs in under two years. Engineers manually cleared flood debris and installed new flood prevention systems. All three power-generating units are now fully operational, marking a major recovery milestone.

"The project's revival in under two years showcases our commitment to energy resilience" - CM Sukhvinder Singh Sukhu
Himachal: Larji Power Project restored and fully operational once again
Shimla, May 18: The 126 MW Larji Hydroelectric Power Project in Kullu district has been fully restored and is operational once again, which suffered extensive damage from the devastating Beas River floods on 9th and 10th July 2023, said an official statement on Sunday.

Key Points

1

Swift restoration completed in record time

2

Rs 245 crore allocated for flood rehabilitation

3

All 3 turbines now operational

4

New flood prevention measures implemented

The project's swift revival, completed in less than two years, was made possible through the timely intervention and strong support of the State Government, helping avert major financial losses.

The State Government allocated Rs 25 crore initially for restoration, followed by Rs 35 crore and subsequently Rs 185.87 crore for the complete rehabilitation of the project. Chief Minister Sukhvinder Singh Sukhu commended the engineers and staff of the Himachal Pradesh State Electricity Board Limited (HPSEBL) for their tireless efforts and commitment to restore the project.

Thanks to their dedication, Unit I of the Larji Power Project was restarted on 15 January 2024 and synchronized with the power grid on 2 May 2024. Unit II followed on 9 August 2024 and Unit III was restored on 17 January 2025. With all three turbines now operational, the project has fully resumed power generation.

The flood had caused heavy deposition of muck deep inside the turbine units, rendering them inoperable for several months. Since mechanical removal was not feasible, the debris was painstakingly cleared by manual effort. To safeguard the project from future natural calamities, several preventive measures have been implemented. Slope stabilisation work, including the installation of cable nets and rockfall barriers, has been completed near the surge shaft gates and is underway at the powerhouse entrance to mitigate risks from landslides and falling debris.

Additionally, a Hinged Gate has been installed at the Main Access Tunnel (MAT) to prevent water ingress during high floods. A similar gate is being constructed at the Emergency Exit Tunnel (EET), with supporting civil works to ensure a secure, watertight system.

In the year 1953, a significant flood occurred at the Larji Hydro Electric Project on the Beas River, which was a historical high flood. This flood, recorded on August 3, 1953, had a discharge of 3,838.37 cumec, whereas the flood that occurred in the year 2023, with a discharge of 5,600 cumec, significantly exceeded the 1953 flood.

Reader Comments

R
Rajesh K.
Great news for Himachal and North India's power supply! 👏 The engineers and workers deserve a standing ovation for completing this massive restoration in record time. Hope the new safety measures will prevent future damage during monsoons.
P
Priya M.
While I appreciate the restoration work, I wonder if Rs 245 crore could have been better spent on diversifying our energy sources. Himachal is becoming too dependent on hydro which is vulnerable to climate change. Solar-wind hybrids might be more sustainable long-term.
A
Amit S.
The 2023 flood discharge was 45% higher than 1953! This shows how climate patterns are changing. Government must conduct similar flood-risk assessments for all Himalayan projects. Jai Hind to the workers who manually cleared all that muck - true dedication!
S
Sunita R.
As someone from Kullu, I'm relieved! The 2023 floods were terrifying. The new hinged gates sound promising but I hope they've also improved early warning systems for downstream villages. Development is good but local lives matter most.
V
Vikram J.
Excellent work by HPSEBL! This project powers so many homes and industries. Just one request - can we get a documentary on the restoration process? Would love to see how our engineers solved such complex challenges. #MakeInIndia
N
Neha T.
The timeline shows amazing coordination - Unit I restored in just 6 months post-flood! But I'm concerned about the environmental cost. Were any ecological studies done before reconstruction? The Beas river ecosystem is already fragile.

We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.

Leave a Comment

Your email won't be published


Disclaimer: Comments here reflect the author's views alone. Insulting or using offensive language against individuals, communities, religion, or the nation is illegal.

Tags: