SC Fast-Tracks JAL Takeover Dispute, Bars Major Policy Shifts Without NCLAT Nod

The Supreme Court has restrained stakeholders from making major policy decisions regarding the Jaiprakash Associates Limited resolution plan without prior approval from the NCLAT. The court requested the appellate tribunal to hear Vedanta's plea on an expedited basis, scheduling it for April 10. Vedanta, represented by Kapil Sibal, argued its revised bid offered significantly higher value than the Adani Group's approved plan. The court acknowledged the limits of judicial review over the commercial wisdom of creditors while ensuring Vedanta's challenge receives a timely hearing.

Key Points: SC Restrains Policy Changes in JAL Takeover, Expedites Vedanta Plea

  • SC expedites NCLAT hearing
  • Restrains major policy decisions
  • Vedanta claims superior bid value
  • Adani's resolution plan approved
  • Limits of judicial review cited
4 min read

SC expedites hearing on JAL takeover dispute, restrains major policy changes without prior NCLAT approval

Supreme Court directs NCLAT to hear Vedanta's challenge to Adani's JAL takeover plan on priority, bars major policy decisions without tribunal approval.

"Rs 3,400 crore higher in gross value... roughly Rs 500 crore more in net present value. - Kapil Sibal"

New Delhi, April 6

The Supreme Court on Monday restrained the monitoring committee or any concerned stakeholder from taking any major policy decision regarding the implementation of the resolution plan for the takeover of bankrupt Jaiprakash Associates Limited without prior approval of the National Company Law Appellate Tribunal.

A bench comprising Chief Justice of India (CJI) Surya Kant and Justice Joymalya Bagchi also requested the NCLAT to hear Vedanta's plea on April 10 on an expedited, out-of-turn basis.

"There is no need to issue any interim direction except that if the managing/monitoring committee decides to take any policy decision, it shall seek permission of the NCLAT," the Court observed.

The Court declined to interfere with the NCLAT's decision approving the Adani Group's resolution plan to take over Jaiprakash Associates Limited. It noted that since the appeal is likely to be decided soon and the appellant's (Vedanta's) interests have been adequately protected by the NCLAT, no further interim directions were necessary.

"Having regard to the nature of the issue and its consequential implications, we request the NCLAT to hear the appeal on an out-of-turn basis. Both sides have assured full cooperation for timely adjudication," the Court noted.

In its plea, Vedanta argued that its revised addendum bid was financially superior, claiming it offered significantly higher value than Adani's plan. Senior Advocate Kapil Sibal, appearing for Vedanta, submitted that its bid was around Rs 3,400 crore higher in gross terms and approximately Rs 500 crore more in net present value.

"Rs 3,400 crore higher in gross value... roughly Rs 500 crore more in net present value," Sibal stated.

He further contended that the NCLAT acknowledged certain issues remained pending but nevertheless proceeded to approve the resolution plan. "NCLAT itself says issues are to be decided, but in the meantime they approve the plan," he argued.

Sibal also submitted that Vedanta had earlier been declared the highest bidder based on value metrics communicated to it. "I received a letter stating I was the highest, both on substantive terms and on NPV basis," he told the Court.

The Court, however, observed that the decision may have been influenced by the upfront payment component, noting that such considerations could have weighed with the Committee of Creditors (CoC). "That may have weighed with the CoC," the CJI remarked.

At the same time, the Court reiterated the limits of judicial review over commercial decisions taken by creditors, observing that such matters fall within their domain of expertise. "The problem is the commercial wisdom and our lack of expertise... at this interlocutory stage," the Bench noted.

Sibal informed the Court that the matter is listed before the NCLAT on April 10.

The Court indicated that, given the pendency before the NCLAT, a time-bound hearing would be appropriate and that a key issue would be whether Vedanta's addendum bid warranted consideration.

During the hearing, Abhishek Manu Singhvi, appearing for the Resolution Professional, outlined the sequence of events leading to the approval of the resolution plan. He submitted that both bidders were aware of the timeline and did not raise objections at the relevant stage. "On November 7, both sides were called... voting was about to start, they left without objection," he said.

He further argued that Vedanta's improved offer came only after the voting process had effectively progressed. "After the process was frozen, Vedanta made a better offer," Singhvi submitted.

The Bench, however, refrained from examining the merits at this stage. "We have our own difficulty; we will not say anything," the Court observed.

The matter is scheduled for final hearing before the NCLAT on April 10, where the tribunal will examine Vedanta's challenge to the approval of the resolution plan.

- ANI

Share this article:

Reader Comments

P
Priya S
Vedanta's claim of a Rs 3,400 crore higher bid is huge! If true, shouldn't the creditors have considered it more seriously? The timing argument is valid, but maximizing value for banks and employees should be the top priority. Hope NCLAT looks at this fairly on the 10th.
R
Rohit P
Another corporate battle between giants. Adani vs Vedanta. At the end of the day, the workers and the thousands of creditors, including many public sector banks, need a swift resolution. This back-and-forth delays revival. The monitoring committee must ensure stability.
S
Sarah B
Respectfully, the process seems a bit messy. If Vedanta was declared the highest bidder earlier based on communicated metrics, what changed? The CoC's preference for upfront payment is understandable, but transparency in such large takeovers is crucial for market confidence.
K
Karthik V
The IBC process is being tested here. The court's restraint is wise—no need for policy flip-flops until the appellate tribunal decides. Speedy hearing is the need of the hour. JAL's resolution has been pending for too long, affecting the entire cement and infrastructure sector.
M
Michael C
Interesting legal dance. The SC acknowledging the limits of judicial review in commercial matters is a mature stance. Let the experts (CoC/NCLAT) decide the financials. The court's role is to ensure the rules of the game are followed, which they seem to be doing.

We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.

Leave a Comment

Minimum 50 characters 0/50