Mumbai-Ahmedabad Bullet Train: 8 Stations Built, Key Bridges & Tunnels Underway

The Mumbai-Ahmedabad High Speed Rail (MAHSR) project is progressing significantly, with eight of twelve station foundations now completed and work actively underway on river bridges and tunnels. The project is fostering substantial indigenous capability, with heavy construction machinery, slab track materials, and specialized equipment now being manufactured in India. Advanced design and safety features, including seismic considerations and indigenous safety devices, are being integrated, with collaboration from IITs. The initiative is also building long-term expertise, having trained approximately 1,000 Indian engineers and skilled workers in Japanese construction methodologies.

Key Points: Mumbai-Ahmedabad Bullet Train Progress: 8 Stations Done

  • 8 of 12 station foundations complete
  • Indigenous manufacturing of track materials & machinery
  • Advanced safety & seismic design
  • Training of 1000+ Indian engineers in Japanese methods
6 min read

MAHSR Project: 8 of 12 station foundations completed; work on river bridges, tunnels underway

MAHSR project advances with 8 station foundations complete. Work on river bridges, tunnels, and indigenous tech boosts India's high-speed rail expertise.

"India will strengthen its position for planning and decision-making in the HSR Sector - Ministry of Railways"

New Delhi, February 12

The Mumbai-Ahmedabad High Speed Rail Project, spanning 508 km, is currently under execution with technical and financial assistance from the Government of Japan. The project is being planned and constructed primarily on an elevated viaduct.

The design for stations on the corridor provides for security measures like controlled entry points, baggage scanners, DFMDs (Door Frame Metal Detectors), CCTV(Closed-Circuit Television) cameras, etc.

The experience and technical capabilities being developed through the MAHSR project, particularly in track construction, advanced signalling, Rolling Stock manufacturing & maintenance, project management etc., are expected to provide a strong foundation for future high-speed rail corridors in the country. With the gain of such expertise, India will strengthen its position for planning and decision-making in the HSR Sector, according to an official release from the Ministry of Railways.

This information was provided by the Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology, Ashwini Vaishnaw, in a reply to questions in the Lok Sabha.

Long-span steel truss girders are being fabricated in Indian workshops, supported by analytical modelling and field measurements to strengthen domestic HSR design capability. Heavy construction machinery used for full-span launching has been indigenised and is now being manufactured in India. Most slab track materials and specialized track machines are being developed and produced by Indian manufacturers, boosting domestic manufacturing capability. Design variations and detail regarding dynamic analysis are being handled by Indian agencies in collaboration with IITs, with advanced dynamic analysis tools and design charts developed to build long-term HSR expertise.

For innovation, the full-span launching method was adopted for the first time to launch 40 m prestressed box girders (~1000 MT), enabling faster launch times of 16 hours. Indigenous noise barriers are being installed along the elevated corridor to minimise noise for nearby residents. Advanced simulation tools for OHE-pantograph interaction and a simulation model for designing the traction power supply were developed with IIT Delhi for accurate design and planning. An underground station is being constructed with provision for a future 90 m high building on the same foundation. Indigenously developed Rail Turnover Prevention Device (RTPD) is introduced to enhance safety during derailments, the release noted.

Indian Engineers and Skilled workers (approx. 1000 nos.) have been trained for Japanese methodology, and presently, track works are being executed under their supervision. A Special Track training facility has been created at Surat for training and regular refresher courses.

HSR stations are being designed as city gateways reflecting local identity, with advanced security features such as controlled entry points, baggage scanners, Door Frame Metal Detectors (DFMDs) and Closed-Circuit Television (CCTV) surveillance.

Safety-focused design includes anti-vibration measures, wind-pressure management in station roofs and provisions like anti-vibration hangers, clamps and bolting plates integrated during construction.

Passenger convenience is ensured through ample parking, drop-off areas and seamless multimodal connectivity with coordinated city master planning.

Sustainable and energy-efficient features are aligned with the Indian Green Building Council (IGBC) Platinum standards.

Greater emphasis has been put on Geo Technical Investigations (GTI) to be sure of structural adequacy and to rule out the possibility of geological surprises.

The GTI has been generally carried out at 100 m, and at shorter intervals in case of special structures. A new geotech lab has also been set up, as per the release.

A high level of security has also been adopted for operational areas and buildings housing sensitive equipment to ensure passenger safety.

Civil engineering structures are designed and constructed as per best international practices, with designs validated by a Japanese High-Level Committee. To enhance earthquake safety, structures have been designed considering relevant seismic zones, with steel and damper stoppers provided on viaducts and bridges to prevent dislodgement, along with the installation of an Earthquake Early Warning System (EQEWS).

The Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is passing through the States of Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.

The entire land (1389.5 Ha.) for the MAHSR project has been acquired. All Statutory Clearances have been obtained. All 1651 utilities have been shifted. The delay in land acquisition in the State of Maharashtra has impacted the project till 2021. The land acquisition picked up in 2022 in Maharashtra, according to a release.

Out of the total 12 stations, foundation works have been completed at 8 stations (Vapi, Bilimora, Surat, Bharuch, Anand, Vadodara, Ahmedabad, and Sabarmati). In the Maharashtra section, foundation work is in progress at 3 stations (Thane, Virar, Boisar), and excavation work at BKC station is near completion, and Casting of base slab started.

17 river bridges have been completed. Work is in advance stage for 4 major river bridges (Narmada, Mahi, Tapti and Sabarmati) in Gujarat & in progress in 4 river bridges in Maharashtra. Work on Depots (Thane, Surat and Sabarmati) is in full swing, the release noted.

Civil works at Bandra Kurla Complex (BKC) are progressing satisfactorily. Excavation works have achieved about 91% progress, and concreting works are at various stages, with 100% completion of the basement slab at Level-4. The work of the under-sea tunnel (approximately 21 km) has commenced, out of which 4.8 km of tunnel between Ghansoli and Shilphata in Maharashtra has been completed.

In line with the Make in India and Aatmanirbhar Bharat initiatives, Indian Railways is promoting indigenous manufacturing of high-speed rail systems and components to reduce import dependence. Building on the success of Vande Bharat, Integral Coach Factory (ICF) in collaboration with M/s Bharat Earth Movers Limited (BEML) is designing and manufacturing high-speed train sets with a design speed of 280 kmph.

Land acquisition for the project has been carried out in accordance with applicable laws, and affected persons have been compensated as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act and relevant State policies. Rehabilitation and resettlement measures, including additional benefits and solatium, have been undertaken in coordination with State Governments.

The MAHSR corridor is designed for high-frequency operations with substantial passenger-carrying capacity. Ticket pricing is proposed to be competitive with respect to existing rail/air travel options. The viability of the project has been assessed on a long-term basis, taking into account projected passenger demand, economic benefits, time savings and regional development.

The Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is the only HSR Project under execution with technical and financial assistance from the Government of Japan. Expenditure amounting to ₹ 86,939/- crore has been incurred on the project till 31.12.2025.

Ministry of Railways has taken up the construction of two Dedicated Freight Corridors (DFC), viz. Eastern Dedicated Freight Corridor (EDFC) from Ludhiana to Sonnagar (1337 Km) and the Western Dedicated Freight Corridor (WDFC) from Jawaharlal Nehru Port Terminal (JNPT) to Dadri (1506 Km), at a total cost of ₹ 1,24,005 Cr. The work on EDFC has been completed and commissioned. In WDFC, 1404 RKm out of a total of 1506 RKm has been completed and commissioned. The balance work on the WDFC from the Vaitarna-JNPT section (102 Rkm) has been taken up.

DFC has contributed to creating additional paths on the conventional network by diverting freight traffic to EDFC and WDFC. Presently, 406 average trains per day are being run on these corridors.

- ANI

Share this article:

Reader Comments

S
Sarah B
The safety features are impressive – earthquake warning systems, anti-derailment devices, and thorough geotech investigations. It shows they are prioritizing passenger safety, which is paramount for a project of this scale and speed.
P
Priya S
While the tech and progress are commendable, I sincerely hope the ticket pricing remains truly competitive as promised. A Mumbai-Ahmedabad ticket should not be a luxury only for the affluent. It must be accessible to the common traveler to justify such a massive investment.
V
Vikram M
The under-sea tunnel work starting is mind-blowing! 21 km is no joke. And 4.8 km already done? This project is pushing our engineering boundaries. Can't wait to take my family on the first ride from Surat to Mumbai.
R
Rohit P
Good to see the land acquisition issues in Maharashtra are being resolved. Delays in such projects are often due to these hurdles. Hope the rehabilitation for affected people was done fairly. The progress in Gujarat section is clearly ahead.
K
Karthik V
The collaboration with IITs for design and simulation is a brilliant move. It bridges the gap between academia and mega-infrastructure projects. This is how we build long-term capability. The noise barriers for residents is also a thoughtful touch.