Bullet Train's Second Palghar Tunnel Breakthrough Achieved with NATM

A major breakthrough has been achieved for the second mountain tunnel (MT-6) of the Mumbai-Ahmedabad Bullet Train project in Palghar, Maharashtra. The 454-meter tunnel was excavated in just 12 months using the New Austrian Tunnelling Method, chosen for the complex geography. Construction is advancing rapidly across Maharashtra, with progress on river bridges, stations, and other mountain tunnels. Overall, the 508-km project has completed approximately 334 km of viaducts, with track laying accelerating in Gujarat.

Key Points: Maharashtra Bullet Train Tunnel Breakthrough in Palghar

  • Second tunnel breakthrough in a month
  • Uses New Austrian Tunnelling Method (NATM)
  • Ensures worker safety with real-time monitoring
  • Part of 7 mountain tunnels in Palghar
  • Project viaducts over 334 km completed
3 min read

Maharashtra: Second Mountain Tunnel of Bullet Train Project set for breakthrough in Palghar

Second mountain tunnel for Mumbai-Ahmedabad Bullet Train breaks through in Palghar using advanced NATM method, marking rapid project progress.

"The excavation was completed in 12 months. - Project Report"

Palghar, February 3

A major breakthrough is set to be achieved in the second mountain tunnel in Palghar district of Maharashtra on Tuesday. This tunnel is 454 meters long and 14.4 meters wide, and it will accommodate both the 'up' and 'down' tracks for the Mumbai-Ahmedabad Bullet Train project.

This will be the second tunnel breakthrough in Palghar district for the Bullet Train project in a single month; the first was at MT-5 near Safale on January 2, 2026. The excavation of the mountain tunnel (MT-6) has been carried out from both ends using the New Austrian Tunnelling Method (NATM), which is a modern controlled drill-and-blast method. The excavation was completed in 12 months.

The NATM method is preferred for complex geographical conditions and uneven tunnel shapes like those found in Palghar, where Tunnel Boring Machines (TBMs) are not suitable. This process does not require extremely heavy machinery, and necessary structural improvements can be made in real-time using shotcreting, rock bolts, and lattice girders. The safety of workers inside the tunnel has been ensured through the use of various geotechnical instruments, real-time monitoring, efficient fire safety measures, proper ventilation, and a controlled entry system.

In Maharashtra, construction work is progressing rapidly across various levels. The longest river bridge of the project, located on the Vaitarna River, has reached the pier level. Foundation work is also underway on other major rivers like the Ulhas and Jagnisarkhya. Construction is in progress at all four stations. Work is also moving fast on the 21 km long tunnel between Bandra Kurla Complex (BKC) and Shilphata, which includes the use of long-span steel bridges at locations crossing national and state highways. A total of 7 mountain tunnels are currently under construction in the Palghar district of Maharashtra.

The progress status of Mountain Tunnels, such as MT-1, is 0.820 km long and 16% complete. MT-2 is 0.228 km long with preparatory work ongoing. MT-3 is 1.403 km long and 41% complete. MT-4 is 1.260 km long and 32% complete. MT-5 is 1.480 km long, 57% complete, with breakthrough achieved on January 02, 2026. MT-6 is 0.454 km long, 47% complete, with a breakthrough scheduled for today. MT-7 is 0.417 km long and 29% complete.

The total length of the Mumbai-Ahmedabad High-Speed Rail (MAHSR) project is approximately 508 km, consisting of 352 km in Gujarat and Dadra & Nagar Haveli, and 156 km in Maharashtra. As of January 27, 2026, approximately 334 km of viaducts, 17 river bridges, and 12 major crossings over national highways, railways, and other infrastructure have been completed. Track laying and electrification work are progressing rapidly in the Gujarat section of the project.

- ANI

Share this article:

Reader Comments

P
Priyanka N
While the engineering is impressive, I hope the environmental impact in Palghar's sensitive zones is being properly managed. The article mentions safety for workers, which is good, but what about the long-term ecological cost of these mountain tunnels?
R
Rohit P
Amazing to see such detailed progress reports. 12 months for a mountain tunnel is fast! This project will be a game-changer for connectivity between Maharashtra and Gujarat. Hope the timelines are met.
S
Sarah B
The scale of this project is mind-boggling. 7 mountain tunnels just in Palghar! The real-time monitoring and safety measures are reassuring. Hope this sets a new standard for infrastructure projects across the country.
A
Aman W
Good news, but the cost is enormous. I wonder if this money could have been better spent improving our existing, crumbling railway network first. The bullet train will only benefit a small section of society who can afford the tickets.
K
Kavya N
As someone who travels frequently between Surat and Mumbai for work, this project is a dream come true. The time saved will be incredible. Jai Hind! 🇮🇳 The progress in Gujarat section seems faster though, hope Maharashtra catches up.

We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.

Leave a Comment

Minimum 50 characters 0/50