Bihar: Bailey bridge work on Vikramshila Setu nears completion
Bhagalpur, May 25
Construction work on the Bailey bridges at Bhagalpur's Vikramshila Setu is progressing rapidly, with authorities aiming to restore traffic movement on the crucial route soon.
The work is expected to bring relief to commuters after the bridge remained closed following the collapse of a slab earlier this month.
According to Superintending Engineer of the Border Roads Organisation (BRO), Vipin Kumar Chand, one of the three planned Bailey bridges has already been fully launched, while the second is in the final stages of decking and finishing work. Preparations for the third bridge are also underway.
Speaking to ANI, Chand said, "In total, three Bailey bridges are planned. Of these, one has been fully launched, while the second is now undergoing decking and finishing work. These smaller tasks will take two to three days to complete. Preparations for launching the third bridge have already begun. The bridges are single-lane. The administration will decide which types of vehicles are permitted to use the bridge. One bridge is complete, the second is nearing completion, and the third will follow the same process. We are making every effort to meet the deadline, as people are facing difficulties and delays. We aim to restore movement as quickly as possible."
Earlier, Bihar Public Works Department Minister Kumar Shailendra said repair work on the damaged Vikramshila Setu is progressing quickly, and the bridge is expected to become operational again within 10 to 15 days.
After inspecting the site, Shailendra said the government took immediate action after a portion of the bridge collapsed earlier this month.
"Immediately after this bridge collapsed, CM Samrat Choudhary, the Secretary, and I held a meeting. We prepared a detailed plan to fix it right away. We will have it operational again within 10 to 15 days," he said.
The minister added that repair work on the damaged sections is being carried out transparently.
On May 3, a slab between two pillars of the Vikramshila Setu, which connects the Purvanchal region with Seemanchal across the Ganga river, collapsed. Following the incident, district officials and senior police officers rushed to the spot; traffic was halted, and routes were diverted.
According to reports, a 10-inch expansion joint first subsided, after which a slab near pier number 133 gave way and fell into the river. The bridge, a key link between Bhagalpur and Seemanchal, has remained closed to traffic since the incident.
— ANI
Reader Comments
Commuters are facing hell since May 3rd 😞 Vikramshila Setu is lifeline for Bhagalpur and Seemanchal region. Hope they finish all three bridges in time and don't delay further. Single lane will be chaotic but at least better than nothing.
Impressive work by BRO - one bridge already launched and second nearly ready. The 10-15 day target seems ambitious but achievable. Bailey bridges have proven effective in disaster situations worldwide. 🚧
Honestly, why did it take so long to start repairs after the slab collapse on May 3? 😤 Lakhs of people depend on this bridge daily. At least now they're working day and night. But someone should be held accountable for the poor maintenance that led to the collapse.
Bailey bridge construction in 10-15 days is remarkable engineering work. Technical specifications - single lane but at least it will restore connectivity. Hope the administration allows heavy vehicles too with proper weight limits, otherwise supply chains will still suffer.
Major respect for BRO and PWD teams working in heat to restore this vital link 🙏 Families in Seemanchal are cut off from medical facilities and markets. Chief Minister's team is on it. But next time, please do regular inspection of expansion joints - a 10-inch failure shouldn't happen.
We welcome thoughtful discussions from our readers. Please keep comments respectful and on-topic.